Hull flexes CPO muscle on Fruit Market regen
Affirming its commitment to the district’s ongoing regeneration, the city council is pushing on with plans to acquire Pier Court off Queen Street by compulsory purchase order.
The crux of the matter is that Hull City Council and its long-term regeneration partner Wykeland Beal want to see the site, a key gateway plot, brought up to standard with the regeneration that has been invested in across the Fruit Market area. The current owner has put forward plans, but so has Wykeland Beal.
Hull’s cabinet will next week be asked to sign off delegated authority that will allow offices to pursue CPO use at the address, 64 Queen Street, if a deal cannot be reached with owner Queensway Properties.
Pier Court comprises 28 apartments, some of which are tenanted.
Neither Fruit Market LLP – the regeneration vehicle taking forward regeneration projects in the area – or Wykeland Beal, which has acted for the LLP in relation to Pier Court, have CPO powers, hence the council taking up the mantle, having used CPO elsewhere in the Fruit Market in the early 2000s, according to the officer report.
Wykeland Beal is a joint venture between two high-profile local development firms, commercially-led Wykeland Group and Beal Homes. The partners in the LLP are Wykeland Beal and the council, with the registered office being at Wykeland’s HQ.
Two proposals
There are currently two proposals in place for Pier Court.
The first (reference 25/00326/FULL on Hull’s planning portal) comes from the current owner, which outlined the intent to deliver a single-storey extension to the main building, and two storeys to the outbuilding, to create an additional floor. The scheme also included the addition of a bin/bike store, courtyard landscaping, and remodelling the interiors to create 30 flats/bedsits.
The design is by Benchmark Architecture.
At the time of this report, said officers, the landowner has not delivered against this consent, which the report said was secured by a former development partner.
However, the report does say that “some work has recently commenced on site and an initial planning notice has been issued to the council for review”. There is no decision notice recorded on the HCC planning portal however, with the decision still pending according to that source.
The second application (24/00337/FULL) also has its status as pending a decision on Hull’s portal.
Advised on by a team including Framework Architects and Stantec, this was submitted by Wykeland Beal, and puts forward a more comprehensive redevelopment of Pier Court and the surrounding area, with a fuller suite of planning documents filed.
Demolition is proposed. A total of 33 homes are then proposed across two units, split out as five townhouses and 28 apartments ranging between one- and two-bedroom configurations. In design terms, the theme would blend with the nearby properties delivered by the JV.
There would also be 5,886 sq ft of retail floorspace across the two blocks, which are billed as The Smokehouse Block and Pier Court Block, which would also have a courtyard with 11 car parking spaces.
The background
Wykeland is the city’s most prominent developer and the JV with Beal has spearheaded the Fruit Market area’s regeneration over the last decade.
This, as reported by officers, has seen many properties in the Humber Street area saved, refurbished and repurposed, with 120 new homes, a 60,000 sq ft head office for a local organisation and a 350-space multi-storey car park developed.
Pier Court which was not factored int to the original masterplan due to the proximity of Wellington House, now demolished – is described as “the only property not to have been either refurbished or demolished and redeveloped on Humber Street”
Wellington House’s removal, on grounds of its dangerous condition, has brought Pier Court, a prominent block at the junction of Humber and Queen Streets, into a harsher light. The officer report said that it “has fallen into poor condition over time” with a 1990s remodelling removing full height windows.
In more recent years, it is recorded, the building – still part-occupied – has been covered in a polystyrene external insultation render. Officers sum up: “The overall condition of the building is poor, and it would take considerable investment to bring it back into a good quality, habitable condition.”
Rounding off the Fruit Market’s regeneration is a priority, as stated in the HCC city centre vision. Thus, sum up officers, “To complete the Fruit Market Masterplan and achieve maximum regeneration benefit for this area, it is essential that the redevelopment of this key cornerstone property and site progresses.”
Will CPO use be needed?
As set out in the officer report, “Wykeland Beal acting on behalf of the Fruit Market LLP has made considerable efforts, dating back to 2021, to engage the property owner and negotiate a fair sale, but the owner has rejected offers made, despite the most recent offer including a premium above the current valuation.”
Officers summed up: “Utilisation of CPO powers would help to secure a sustainable and achievable regeneration of a prominent site and allow the regeneration of the small adjoining plots to deliver a significant improvement to the area.
“If Pier Court is not purchased this comprehensive scheme cannot go ahead in a cohesive well-planned manner and it creates further financially viability issues due to the smaller apartment numbers, making wider development unlikely to proceed.”
Hull’s cabinet meets on 23 November.