Network Rail hopes to complete the £10.7bn project in the 2030s. Credit: TransPennine Express

Where is Network Rail’s £11bn Transpennine Route Upgrade up to?

Enhanced stations, route electrification, and track improvements – 2025 was a busy year for the railway programme, which aims to improve journeys on the 76-mile stretch that includes Manchester, Huddersfield, Leeds, and York.

What is it?

The £10.7bn Transpennine Route Upgrade project is due to complete in the 2030s, having electrified the entirety of the railway line, doubled the number of tracks at certain locations to enable faster trains to overtake slower ones, installed digital signalling, and improved accessibility across the 23 stations on the route.

The TRU masterplan also has ambitions to improve freight travel in the North, by widening tunnels and creating 15 more freight paths. This work, Network Rail estimates, will remove the need for more than 1,000 lorries a day.

What’s been done so far?

More than a quarter of the 76-mile route has now been electrified. This includes the section from Manchester Victoria to Stalybridge and from Church Fenton to York – the latter of which completed in August last year.

In October, a £46m train maintenance centre at Hillhouse Depot opened in October near Huddersfield.

Work has also been ongoing regarding improving Huddersfield Station, with the station partially reopening on 29 September after a 30-day closure. This was to enable the rebuilding and extension of three platforms at the station, a variety of track upgrades, and the installation of digital signalling.  This year, another platform will receive upgrades as will the station’s track and canopy. This aspect of the scheme should complete in early 2027.

Also in Huddersfield, the viaduct had new bridge beams installed.

Network Rail’s team closed out 2025 by realigning tracks at Mirfield and demolition Whitacre Street overbridge in Deighton. The group has also installed 70 signals and remodelled more than three kilometres of track at Church Fenton station, which itself had two platforms realigned.

Overall, TRU has seen the installation of 40 miles of track and the laying of 30 miles of cable roughing. Network Rail also built 1,000 overhead line equipment foundations to support electrification across the route.

“This year has produced so many achievements and what we’re doing across the programme will not just improve journey times and reliability, but better connect towns and cities across the North,” said  James Richardson, managing director for the Transpennine Route Upgrade.

“TRU is a key enabler to unlock potential in our communities and support regional economic growth, and we are looking forwards to another successful year in 2026.”

What can we expect in 2026?

Work will continue on improving Huddersfield Station. Network Rail has also commenced build a 1,150-feet viaduct over the River Calder at Ravensthorpe, a project that is due to complete in summer 2027.  Expect to see updates on the extension of Ravensthorpe Station as well, which is being rebuilt to be accessible. The station will reopen in March 2028.

Your Comments

Read our comments policy

Related Articles

Subscribe for free

Stay updated on the latest news and views in Yorkshire property

Subscribe

Keep updated on the latest news, deals, views and opportunities in Yorkshire property, in your inbox.

By subscribing, you are agreeing to Place Terms & Conditions and Privacy Policy.

"*" indicates required fields

Your Job Field*
Other regional Publications - select below
Your Location*